North Port Manhole Rehabilitation

North Port Before
Deteriorated North Port manhole before SewperCoat® rehabilitation
North Port Manhole Before SewperCoat® Rehabilitation

BEFORE: Existing manhole condition with failed epoxy coating and severe substrate deterioration.

previous arrow
next arrow

The existing epoxy coating in this North Port manhole had failed, leaving the underlayment and concrete substrate severely deteriorated. After 5,000 PSI water blasting removed the remaining unsound material, extensive surface loss was exposed and the existing bench required complete reconstruction.

Maxx Environmental rebuilt the deteriorated areas and constructed a new bench using SewperCoat®, applied at depths of 2 to 3 inches to restore the manhole structure.

Learn more about our SewperCoat® manhole rehabilitation services throughout Florida.