SewperCoat® Lift Station Rehabilitation: Lakeland, Florida

Lakeland Before
orlando-fl-lift-station-before-liner-infiltration.jpg
Lakeland Lift Station Rehabilitation: Failed Epoxy Liner

BEFORE: Failed hard epoxy liner with groundwater infiltration through the bottom seam and pipe invert.

previous arrow
next arrow

Maxx Environmental completed a lift station rehabilitation project in Lakeland, Florida, involving a 6 foot diameter, 25 foot deep structure with a failed hard epoxy liner. Groundwater infiltration was present along the bottom seam and at the pipe invert.

Crews mechanically removed the deteriorated epoxy lining using pneumatic chipping hammers and sealed the active leaks before applying SewperCoat® at a minimum thickness of 1 inch.

The completed SewperCoat® lining is backed by the manufacturer’s (Imerys) 10-year warranty.

Learn more about our SewperCoat® lift station rehabilitation services throughout Florida.