This Key Largo WWTP rehabilitation project involved a 30-foot by 140-foot aeration chamber where the existing epoxy coating had failed, allowing effluent to migrate behind the coating and leak through vertical joints and seams in the concrete structure.
Maxx Environmental removed the failed epoxy using 40,000 PSI water blasting and applied approximately 3,400 square feet of SewperCoat® at a 1-inch thickness. The completed rehabilitation sealed the chamber and eliminated the leaks.